According to Bloomberg, some banks are delaying a $6.6 billion Bridge facility. Other financings face participant refusals, rather than confirmed wholesale cancellations.

By Wellinton Oliveira, CEO of Lyntev. Published: 25 November 2026, 22:20.

https://news.lyntev.com/news/data-centre-loans-chip-restrictions

## Key points

- Some lenders seek further checks on Bridge Data Centres financing, Bloomberg reports.
- One bank declines Digital Halo participation; at least one fund steps away from GMI Cloud financing.
- The Aolani reassessment is context attributed to the previous week, rather than a new 25 November decision.
- The private reports lack independent confirmation and establish neither losses nor cancellation of every loan.
- The US rule has applied since 19 November, with conditions and exceptions; it does not confirm individual banks’ actions.

Lenders are delaying decisions on loans for data centres serving Chinese companies, according to a [Bloomberg report republished by Yahoo Finance](https://uk.finance.yahoo.com/news/billions-data-center-deals-grind-160100809.html). The 25 November report identifies extra caution around a $6.6 billion Bridge Data Centres facility and participants pulling out of other financings. It does not describe the wholesale cancellation of all those loans.

The information comes from people familiar with private negotiations. We found no independent confirmation of the decisions attributed to individual lenders. The report was published at 16:01 Lisbon time; that is its publication time, rather than a verified date for every lending decision.

## Bridge: further checks do not mean the loan is cancelled

Bridge Data Centres, owned by Bain Capital, is seeking financing expanded to $6.6 billion. Bloomberg says some lenders are taking longer before proceeding and conducting additional checks. The company's Malaysian facilities serve customers including ByteDance, people involved in the discussions told the agency.

The figure is the size of the proposed facility, rather than money those banks have already lost. The report does not identify every lender delaying a decision or say the entire financing has been abandoned. Bain referred Bloomberg's questions to Bridge, which declined to comment. ByteDance did not respond to the agency.

## Three loans, with decisions that cannot be added up as losses

The table separates facility amounts from the actions attributed to participants. All come from the 25 November report; it gives no individual dates for these decisions.

| Financing | Loan amount, US$ million | Decision reported by Bloomberg | Time reference |
| --- | ---: | --- | --- |
| Bridge Data Centres | 6,600 | Some lenders delay proceeding for further checks | Report dated 25 November |
| Digital Halo | 372 | One bank declines to participate; others ask more questions | Report dated 25 November |
| GMI Cloud | 300 | At least one fund declines to participate | Report dated 25 November |

For Partners Group-backed Digital Halo, the agency describes a loan for a Malaysian data centre. The facility serves Alibaba and other customers. One bank's refusal does not, on its own, establish that the entire financing has ceased to exist.

GMI Cloud's loan would fund chips for a Thai data centre to be used by Tencent. At least one fund's refusal likewise does not establish the project's final outcome. Adding the three rows as a confirmed loss would confuse requested amounts with decisions about financing.

## Aolani is context from the previous week

The same report mentions a $480 million loan for Aolani, a Singapore-based cloud computing company with business linked to ByteDance. But it attributes the reassessment by several banks to information from the previous week. That episode should not be presented as a fourth decision taken now.

There is another timing distinction: Bloomberg says it previously reported client reviews by lenders including Citigroup and Standard Chartered. The current article brings together that background and specific decisions. It does not establish that every institution has adopted the same response or stopped all lending to the sector.

## The rule covers remote access and has its own conditions

The US Bureau of Industry and Security, or BIS, [announced the measure on 16 November](https://media.bis.gov/press-release/bis-issues-rule-addressing-remote-access-american-super-intelligence-technology). The [rule published in the Federal Register](https://www.govinfo.gov/content/pkg/FR-2026-11-19/html/2026-23529.htm) took effect on 19 November. Section 744.24 covers certain transactions involving data centres supplying significant computing capacity remotely to companies in the designated destinations, including China and Macau.

For existing services covered by the rule, the text provides a 90-day window to obtain a licence. It also contains exceptions, including commercial recommendation systems. It is neither a blanket ban on all computing rentals nor an administrative decision on the loans in the table.

The rule confirms the regulatory framework. It does not confirm the checks, withdrawals by lenders or private terms of individual contracts described by Bloomberg.

## Credit, chip ownership and rented capacity are different things

An [earlier article on this portal](https://news.lyntev.com/news/nvidia-gpu-resale-capacity-china) distinguishes offers to sell processors from contracts for the use of computing capacity. This report adds another layer: who is willing to provide financing.

These are different objects. A machine offered for sale is not a completed sale. A rental rate is not a server's purchase price. Nor does a loan under consideration automatically represent a loss to its lender. The sources do not establish that all these transactions involve the same equipment.

## Final lending decisions and financing terms remain unconfirmed

Digital Halo, Aolani and Alibaba did not respond to Bloomberg. Partners Group declined to comment. GMI Cloud and Tencent also did not respond. These are responses recorded by the agency, rather than approaches made by this portal.

The final composition of lending groups, each facility's terms and the completion or restructuring of the deals remain unconfirmed. The report documents hesitation and refusals by participants described by its sources. It does not establish that the data centres will never be built or that every Chinese customer has lost access.

## Sources

- [Billions in Data Center Deals Grind to Halt After AI Chip Curbs](https://uk.finance.yahoo.com/news/billions-data-center-deals-grind-160100809.html), Bloomberg — Sheryl Tian Tong Lee, Kari Soo Lindberg, Aileen Chuang e Megawati Wijaya
- [BIS Issues Rule Addressing Remote Access to American Super Intelligence Technology](https://media.bis.gov/press-release/bis-issues-rule-addressing-remote-access-american-super-intelligence-technology), Bureau of Industry and Security
- [Addressing Remote Access to Advanced Semiconductors; Interim Final Rule — 91 FR74970,2026-23529](https://www.govinfo.gov/content/pkg/FR-2026-11-19/html/2026-23529.htm), BIS / Government Publishing Office

## Topics

- [Data centres](https://news.lyntev.com/topic/data-centres)
- [Export controls](https://news.lyntev.com/topic/export-controls)
- [Semiconductors](https://news.lyntev.com/topic/semiconductors)
- [China](https://news.lyntev.com/topic/china)
- [Nvidia](https://news.lyntev.com/topic/nvidia)

Published by Lyntev News, a portal by Lyntev (https://lyntev.com/en).